WBS Charts
Today we are going to make a WBS chart. There are a few videos in the tool tab.
Keep the chart simple. Put the build plan on one flow line, the paint plan on a second flow line, the electrical system on a third flow line and the control system on a fourth line.
An example of the start of your WBS assignment.
Create a WBS for the Boiler project use the topics in the Rubric below as a guide.
Please turn in your homework in the assignment tab, WBS homework on Brightspace
Description | Ignored=0 | idea attempted=5 | 50% complete= 10 | 100%=20 |
---|---|---|---|---|
Chart labeled correctly header | project name | Team names | total hours presented of entire project including project management team | |
scenery plan | Collaboration with other areas of project | steps of 1or more day of work per step presented | total scenery work time presented | |
paint plan | Collaboration with other areas of project | steps of 1or more day of work per step presented | total paint work time presented | |
electrical plan | Collaboration with other areas of project | steps of 1or more day of work per step presented | total electrical work time presented | |
control system plan | key connections recognized | steps of 1or more day of work per step presented | total control work time presented |