Case 51: Concrete Walls

Cellia Ait-Ouaret

ARCH4861

03.12.2019

Case 51: Concrete Walls

Upon Reading Case 51, we encountered many discrepancies that lead to an unpleasant outcome for everyone involved in the project. The written bid should have referenced the architectural drawings, given that there was missing information on the structural drawings and the subcontractors use the structural drawings to complete the work due to the amount of detail structural drawings provide. The general contractor should have never accepted any bids without referencing the specific drawings to be used for the work. A list of the pages, both signed and dated, should have been made to avoid any confusion. The general contractor should not have allowed the subcontractors to start any work without a signed contract.

Leave a Reply

Your email address will not be published. Required fields are marked *