Case 51: Concrete walls

 

Case 51: Concrete walls  

 

In this case we have a General contractor who was commissioned to build a 10-story office building. One of the main problems happening in this project is the lack of communication and professionalism. The Contractor decides to hire a sub-contractor to do the concrete form-work of the project. When the General Contractor sends out the documents for bidding the bidder did not referenced any of the drawings from the documents in his bid. In the Interview between the General Contractor and the sub-contractor the General Contractor took the sub-contractor’s word about getting all the work done instead of making an agreement on paper. This leads to walls not being installed in the project and the sub-contractor refuses to install the walls. The walls are worth $50,000 and there’s is no budget to install the walls. In this case the General Contractor is the one to blame for this problem because he should’ve never agreed to the bid knowing that the bid made by the subcontractor was low and because the subcontractor did not reference his bid to any drawings in the list. 

 

Leave a Reply

Your email address will not be published. Required fields are marked *