Case Study 51: Concrete Walls

After my company was selected as the GC for a 10-story office bldg, we sent out bids for the concrete package,  and  3 subs have tight bids within 3%  off each other. the scope of work includes framework, rebar, pour, and finish. the concrete and pump will be taken care of by my company.

after the lowest bidder was selected there was an interview conducted with the subcontractor to make sure the scope of work and schedule are covered. their bid did not reference any drawings, but in the interview, they mentioned that the concrete work was shown on both architectural and structural drawings. This was asked because there were some concrete housekeeping pads, and steel stair infill was shown on arch, drawings and wanted to make sure that it was picked up. The sub acknowledged this and notes on this were taken on pre-award meeting notes.

The contract was awarded and the agreement was sent around the time the work began. the sub calls back asking why there was a reference made to the arch. drawings and we remind him of the housekeeping pads and stair infill. 2 weeks later the sub sends the signed agreement but the reference to arch drawings is crossed out. several walls were shown on the arch drawings but not on the structural drawings.

An (RFI) is written and structural engineer responds with appropriate sketches, but the architect does not attach a directional document such as a (CCD) to the (RFI). As a result, the sub refuses to accept the contract as originally written, and will, not install the walls unless a change order is issued. the walls are worth $50K and my company or the sub don’t have the funds to make amends.

In this case, the bid from the subcontractor should not have been accepted in the first place without seeing their architectural and structural drawings to make sure that everything was being acknowledged. the sub should have also not crossed out the reference to the architectural drawings on the agreement and the architect should have attached a directional document. the architect, GC, and sub all share faults for not communicating properly.  Although the owner was not involved directly, he would have to, unfortunately, put up money for the work to be done properly.

Case Study 24: Budget or Build?

In this case, the main issue was that many agreements made between the client and the general contractor were only discussed verbally and not documented. In this case, the client contracted a GC and an Architect separately for the design of the $3 million executive home.  Once the permit was approved, the architect’s contract was closed out.

In the contract, the GC discussed in details what could be reimbursable, but it did not tie the GC to a fixed price. In the contract, the $3 million were referred to as the “budget”. The owner assumed that this amount was the lump-sum agreement because of verbal discussions and early “bid” estimates prior to the contract agreement. During the project, many changes had to be made mostly due to building code.

The GC believed this was a (T&M) time and materials project, therefore he felt that paperwork for change orders on a budgeted amount was not necessary. at 90% completion, the GC invoiced the owner for the 100% payment and also indicated that the project would overrun $500K. The owner then refused to pay the GC. the GC then pulls off the job and will not complete the work until the owner pays off remanding $1 million and the additional $500K, at that point the GC is dismissed by the owner and both parties sue each other.

Legally I believe that firstly the GC cannot pull off a job. The GC is at fault for not completing his part of the contract and abandoning the job. However, the owner is also at fault for not contracting a third party owner’s rep or agency construction manager involved that would’ve helped him out as this was his first time being involved in a construction project. The GC is also at fault for not submitting or notifying the owner about the changes that had to be made due to the building code. In order to avoid this situation, there should have been a fixed price set and the architect’s contract should’ve not been closed out until final completion as he would’ve had control in the situation. In this case, I believe that the owner has to pay the GC the remaining $1 million from the contract, but the $500K should be the responsibility of the GC as he never notified the owner of ongoing changes to the project.

Architect: Yes or No?

Kevin Carrillo

I believe that this question generates a debate within those currently studying architecture. Personally, I would like to one day become a Registered Architect. I believe that obtaining this license will open more doors in the future. Although it’s time-consuming  I would like to one day see my hard work pay off. Becoming an RA would allow me to be more involved in the design process and eventually sign-off on projects. I believe that becoming an RA would be somewhat like a capstone to my education as it is my main goal and my main motivation in school. Achieving this license will allow me to work on my own and also start a firm if the opportunity shows up. Although it’s a dream to work at a major firm, I want to be able to do it as an Architect and lead people. obtaining this license would not only allow me to work as an architect but if ever needed a consultant as well.

The journey is not easy and I want to look back one day and say that it was worth it! I wouldn’t be at peace with myself knowing that I spent countless hours working on projects and to not go all out for the ARE. I know that there’s a lot of work that still needs to be done but my main focus on becoming a Registered Architect is still on sight. I like taking on new challenges in life and working in different projects will help me to further expand my knowledge of the different aspects of Architecture. In this area of study, one can never stop learning and that also motivates me to keep moving forward.  With these thoughts in mind, I will continue to learn and strive towards reaching my goal of becoming an Architect in New York!

Dream Job-Kevin Carrillo

Since I was young, I’ve always been interested in the design & construction field. I always enjoyed watching how different elements were brought together to form massive structures. In my head, I would always look up at those tall buildings and think to myself that one day I would design such structure. I was always interested on the hands-on design projects in high school, but they were more focused on the engineering aspect. However, I was always interested in the design process. I liked the idea of starting something from scratch and build on from it to complete a finished product. Here at NYCCT I learned that architecture is more than focusing on the beauty aspect of a facade. I’ve learned that architecture means to take into consideration various different aspects of a site and fully develop it to generally solve a problem. I enjoy studying Architecture as it not only allows us to learn from past world history and design methods, but to also push towards new and innovative technology that is beneficial to our planet (green /LEED) designs, while at the same solving problems that will benefit people.

As for my dream job, I would like to first continue my education after completing my bachelor’s degree and work towards my Master’s degree in one of the following: Architecture, Urban Design, Landscape Architecture,  or possibly in the Construction Management-related field. As for work; I’d currently like to get an internship or part time/full time job at a small firm as this will allow me to learn more about the procedures taken in the AEC field. Although, it could be more work compared to a larger firm, I would like to get basic knowledge of different type work done in an actual architectural project to fully understand every step from beginning to end. eventually, I would like to work for a bigger firm and possibly work on projects all over the world. I would like to gain as much experience possible and in the future take the ARE and hopefully become a Registered Architect someday. Maybe someday open my own firm, but there is a vast amount of work to be done; therefore I’m working on learning as much as I can now in the present to eventually make everything easier in the future!