Event | Planned Start Date | Planned End Date | Actual Start Date | Actual End Date | Reason for change |
Planning, Outline and Blueprinting. | 09.21.21 | 09.30.21 | 09.21.21 | 11.15.21 | I was changing the project and adapting while building. If I did not like the way a certain feature looked or behaved I would improve it or remove it. |
Programming | 09.24.21 | 11.28.21 | 09.30.21 | 12.06.21 | I would be testing and fixing issues I found. Which lasted a while |
Search, Pick and Implement Assets | 10.01.21 | 11.12.21 | 11.12.21 | 11.24.21 | I delayed this towards the end because I did not find it as important as having a working project. |
Finishing Touches | 11.26.21 | 12.02.21 | 11.30.21. | 12.06.21 |