Planning, Outline and Blueprinting.09.21.2109.30.2109.21.2111.15.21I was changing the project and adapting while building. If I did not like the way a certain feature looked or behaved I would improve it or remove it.
Programming09.24.2111.28.2109.30.2112.06.21I would be testing and fixing issues I found. Which lasted a while
Search, Pick and Implement Assets10.01.2111.12.2111.12.2111.24.21I delayed this towards the end because I did not find it as important as having a working project.
Finishing Touches11.26.2112.02.2111.30.21.12.06.21