Author Archives: D. Occeus

Class Minutes_03/14/18_Danie Occeus

March 14, 2018

Professor Mishara briefly mentioned what was cover on March 7, 2018, and also announced that the guest speaker will be a professor from the architectural department with insights about international studies.

What we discuss:
Continuation and break down of AIA Document B101
Sample copy handed out by the professor in class attached with a list of suggested architectural articles for the reading assignments that are soon due.

Major point cover in class: Architect /Owner Agreement

  • Substantial Completion
  • Scope of service
  • Level of care
  • Insurance
  • Bidding/negotiation
  • Site observation
  • Acceptance of work
  • Payment of contractor
  • Submittal change of work

Phase of service

  • Schematic
  • Design development
  • Construction documents
  • Construction phase

Cost

Task
• Review the progress of the final project with all groups
• Go over question sheets and be familiar with the terms
• Prepare for upcoming submission of a summary of the first article
• Start preparing a semi portfolio composed of 5 major work

Plan of action
Next week we will go over the question sheet
Discuss further the construction document of architect basic service