INSTALLATION VIDEOS-TENLY LAW

TIME STAMPS:

0:03-0:12 SPIDER CLIP ASSEMBLY

0:16-0:26 GLASS PANEL ASSEMBLY

0:28-0:53 GLASS PANEL AND SPIDER INSTALLATION ASSEMBLY

TIME STAMPS:

1:36-2:35 STEEL FRAME INSTALLATION

2:42-2:53 LOWER STEEL WALL INSTALLATION

2:55-3:15 MORE STEEL FRAME INSTALLATION

3:17-6:06 REPITITION OF STEEL FRAME AND STEEL WALL PANEL INSTALLATION

Video Research – VMZINC (DRI-DESIGN) AND 1600SS CURTAIN WALL (KAWNEER) – DOLMA TSERING

VMZINC (DRI-DESIGN)

1:18 – BRACKETS INSTALLATION

1:28 – RAFTERS FIXED TO BRACKETS

1:33 – PERFORATED BASE TRIM INSTALLATION

1:51 – INSTALLATION OF INTERLOCKING PANELS

2:30 – INSTALLATION OF SPLICE PLATE

3:13 – FLASHING INSTALLATION

1600SS CURTAIN WALL (KAWNEER)

2:58 – INSTALLATION OF RAIL

3:04 – APPLYING SEALANT

4:14 – SETTING CHICKEN HEAD

4:59 – INSTALLING ANCHOR

6:19 – INSTALLATION OF CRITICAL SEAL

9:04 – SETTING THE UNITIZED PANEL

 

Modified Grading Percentages & Class Schedule – All sections

To accommodate the loss of time and the modified schedule for the Spring of 2020 we have updated the grading percentages for the various projects assigned this semester.  We will spend the rest of the semester focused on the two 3D model assemblies (Opaque & Glass Curtain Wall).

We will not go back to working on the Revit drawing set.  Each professor will notify you about any additional collection dates for this drawing set.

Updated Schedule
WK Topic Tuesday Thursday
Week 1 Exterior Backup Wall 14-Apr 16-Apr
Week 2 Curtain Wall Systems Overview 21-Apr 23-Apr
Week 3 Structural Glazed Curtain Wall 28-Apr 30-Apr
Week 4 Parapets & Footings 5-May 7-May
Week 5 Windows & Doors 12-May 14-May
Week 6 Final Presentations 19-May 21-May