Schedule for this project
1. Draw several concepts on paper with dimensions and specifications.
+ (Week of July 2 through July 18)
2. Determine the best concept to focus on.
+ (Week of July 23 through July 25)
3. Create a digital replication of the selected concept using a computer program.
(AutoCAD, Solidworks, or Pro Engineer)
+ (Week of July 30 through August 1)
4. Attempt to make a live model of the concept (either large scale or small scale).
+ (Week of August 6 through August 16)
5. Analyze it’s efficiency and practicality.
+ (Week of August 20 through August 30)
————————–