Randal Umpierre 7-25-13 Literature Review 3 Introduction of a new Energy Recovery System – Optimized for the combination with renewable energy by Kay Paulsen, and Frank Hensel This article is about introducing a new energy recovery system into existing … Continue reading
Posted in Uncategorized
Leave a comment
To do list-7-23-13 + Summarize the second paper that you read last Thursday-complete + Finish reading a third paper that you decided to read-complete + Follow the schedule you created-complete + Update what you have done today to the openlab page-complete
Posted in Uncategorized
Leave a comment
Literature review 2
Randal Umpierre 7-23-13 Literature Review 2 A review of energy storage systems in microgrids with wind turbines by Abdorreza Rabiee, Hossein Khorramdel, and Jamshid Aghael This article is about the different types of energy storage systems that can be … Continue reading
Posted in Uncategorized
Leave a comment
To do list (07/23/2013)
+ Summarize the second paper that you read last Thursday + Finish reading a third paper that you decided to read + Follow the schedule you created + Update what you have done today to the openlab page
Posted in Uncategorized
Leave a comment
To do list (07/18/2013)
To do list for 7-18-13 + Summarize the first paper that you read yesterday – Complete + Finish reading a second paper that you decided to read – Complete + Follow the schedule you created – Complete + Update what you … Continue reading
Posted in Uncategorized
1 Comment
To do list (07/17/2013)
+ Make a schedule for the rest of summer. Eg when you want to finish cad modeling etc. + Start developing a design of the bike. + Finish reading one paper that you picked up.
Posted in Uncategorized
Leave a comment
Order of operations list
ORDER OF OPERATIONS LIST FOR ELECTRIC ERS BIKE PROJECT 1. Draw several concepts on paper with dimensions and specifications. (Week of July 2 through July 18) 2. Determine the best concept to focus on. (Week of July 23 through July … Continue reading
Posted in Uncategorized
Leave a comment
Avatar
Randal, When you have a chance, please put your picture as an avatar for your account. So that everyone notices who are working this project. Thanks, MRN
Posted in Uncategorized
3 Comments
To do list (07/16/2013)
+ Start reading the papers you picked up and want to read. + Start making a schedule (this summer) for the research plan. + Start developing a CAD model of the bike with ERS from your hand drawing.
Posted in Uncategorized
4 Comments
Link for “A flywheel variator energy storage system”
http://dx.doi.org/10.1016/0196-8904(96)00007-6,
Posted in Uncategorized
Leave a comment