Neolith Facade USA, Efficient solutions – Spider Fitting

Neolith Facades USA – HC System installation

  • 0:25 – 0:46 Technical features
  • 0:47 – Closing by Concrete block
  • 0:49 Closing by Mat Sheathing
  • 0:53 Closing by OSB panel
  • 1:02 – Addition of Vapor Barrier
  • 1:11 – Installation of Aluminum Brackets
  • 1:19 – Thermal Insulation Installation
  • 1:31 – Used Materials
  • 1:34 – Installation of Vertical Profile T
  • 1:48 – Addition of  Double sided tape on Vertical Profile T
  • 1:54 – Addition of Chemical-Elastic Fixation on Vertical Profile T
  • 1:57 – 2:16 Installation of Stone Veneer Panels
Spider Fitting

  • 0:20 – 0:24 Four ways Spider Fitting

 

 

EQUITONE Facade Panel Installation – Unitized Curtain Wall Installation

  • 0:07 EQUITONE panels visible installation system with rivet or screw
  • 0:09 Invisible fixing method with adhesive
  • 5:13 – 5:28 How rivet works
  • 6:09 The position of the rivet holes on the panel
  • 6:57 Panels on metal supporting frame with fixed and gliding points
  • 7:21 location of fixed points
  • 7:45 Rivet with sleeve for fixed points and without sleeve for gliding points
  • 7:55 Supporting metal frame with anchor points
  • 9:25 Measurement of panel placement
  • 11: 31 Foam  tape on the metal frame
  • 15: The position of horizontal aluminium joint profile
  • 16:43 Invisible adhesive fixing of panels ( supporting frame with foam and adhesive)
  • 17:28 Tergo secret fixing method (Half drilled panel with anchor, metal hook, washer and bolt)
  • 17:44 Hanging Hook system ( hanging hooks on the back of the panel)
  • 18:00 Adjustable top hanging hook

 

  • 2:14 lifted up curtain wall unit ready to be placed into the installed curtain wall frame

 

 

Opaque Material – Rain screen / Cladding Systems

Rain screen / Cladding Systems Start  T=30 End at 205.

  • 30    Shows the cassettes being mechanically folded from one piece of metal with a self-draining-gutter
  • 55 Shows the PPC – Polyester Coating
  • 109 Metallic, standard, and textured to any RAL or BS color
  • 119 Installed over insulated panel
  • 125 Shows first cassette being hooked on the J rail then fixed to the panel
  • 133 Subsequent cassettes hook into the neighbor
  • 152 Showing the different design cassettes.
  • 205 End Here

Stick Curtain Wall Assembly

Timestamps: NOTE WATCH VIDEO @ 2X Speed

  • 0:20 – 0:35 Steel to Concrete Connection
  • 0:41 – Exterior Mullion Assembly
  • 1:00 – Horizontal to Vertical Connection
  • 1:20 – 1:30 – Gasket Installation
  • 1:40 – Lift of mullion onto the concrete slab
  • 2:00 – Use of appropriate Hardware
  • 2:42 – Installation of Glazing
  • 3:17 – Corner Installation
  • 3:30 – Installation of Window Sill
  • Remainder show window disassembly