  • Sept. 7 – Dec. 21         Tues. & Fri. – Research & Project Development

  • Sept. 9th                             Materials Procurement

 

  • Oct. 1st                                CPU Mainframe Complete

 

  • Oct. 19th                             Software Installed with License

 

  • Oct. 13th                            Procure Entertainment Peripherals (Sensors, musical                                                       equipment, etc.)

 

  • Nov.  1st                             Testing I/O Setups

 

  • Nov.  15th                         Configure settings for remote support equipment

 

  • Nov. 25th                        Final Testing and touch ups

 