Problem 4 – F2M

F2M

You are the technical direction team in charge of the scenery crew at New York Stage and Film’s Powerhouse Summer Season. The set shown on the attached drawing (Plates 1-6), is to be built for show to take place in the summer of 2014.

The scenery will be built, installed and painted by the NYSAF production staff. The concept for the show is very realistic, so great care should be taken to make sure the set looks as real as possible. Walls shouldn’t shake; there should be no visible seams in walls. The scenery will be built in the Vassar College Scene Shop, then transported to the Powerhouse Theatre, about a 900 feet away across the campus.

The Details

As a team, you must make a plan for the construction and installation of the scenery for the show. You do not need to plan the painting procedures, but you should account for the cost of paint in your materials estimate. Prepare any documents you think you would need for the implementation of this plan.

When you are planning the documentation, think of who you will be showing it to. You will need to produce a complete budget estimate (materials and labor) on April 24th for approval to purchase materials and hire build crew. You will also need to prepare a build calendar, load-in plan, and construction drawings for the show.

See the Milestones section below for important show deadlines.

See the Labor section below for labor costs.

Checklist for your reference:

Bring the following things to be shared with the class on Thursday, April 24th

  • Your team’s definition of the problem
  • Sketches of your approach to solving the problem –
  • A complete budget estimate for materials and labor (to be turned in as well)

Bring the following things to be shared with the class on Tuesday, April 29th

  • Your team’s definition of the problem
  • Revised sketches of your approach to solving the problem
  • A complete budget estimate for materials and labor – with any necessary revisions (to be turned in as well)

Bring the following to be turned in on May 20th

  • All initial sketches and notes
  • Complete paperwork package (drawings, budgets, calendar… whatever you think you need to communicate your ideas)
  • Any samples or physical tests your team conducted
  • A list of what you learned

Milestones

Event Date
Begin Build June 9th
Load-in (must work out schedule with LX/Sound/Props) June 16th-21st
Lighting Focus and Quiet Time Sunday, June 22nd all day
Tech day 1 Monday, June 23rd noon-midnight
Tech day 2 Tuesday June 24th noon-midnight
Final Dress Wednesday, June 25th 8pm go
Opening Night Thursday, June 26th 8pm curtain

Labor

Title Cost per hour Notes
Master Carpenter $40 1.5x pay after 40 hours in one one week, or after 12 hours in one day. Pay does not return to normal time until one full day is taken off. MC must be called while any carpentry work is happening on site.
Staff Carpenter $25 1.5x pay after 40 hours in one one week, or after 12 hours in one day. Pay does not return to normal time until one full day is taken off.
Carpentry Intern $0 No more than three allowed. Must have one full day off each week. One of these will be on run-crew of the show and is not available during tech week.
Overhire carpenter (casual labor) $100/day 2 day minimum call. 4 day maximum call.

NB: Shop space is tight, and usually no more than 6 people can be working at one time while building.

Grading Criteria

We will use the standard grading rubric for this problem. Your ultimate goal is to achieve a show as close to the designer’s intention as possible. Preparing good construction documents and choosing correct materials will be very important to meeting this goal.

Files for your reference

Designer Drawings: F2M_2011.06.10

AutoCAD drawing of Powerhouse Theatre: https://www.dropbox.com/s/bxvc0w719k2p7it/Powerhouse.dwg

Kitchen Tile Reference:

F2M_0531

Brick reference:Brick Reference 2011.06.12

Model PhotoF2M Model IMG_1015

Carpet Sample

 

Carpet Sample photo.2011.06.13

Leave a Reply