New Schedule
Start Date | End Date | Description | Duration |
1/21/17 | 2/20/17 | Prep/Planning | 31 days |
2/1/17 | 2/20/17 | Ordering Equipment/Accessories | 20 days |
3/18/17 | 3/23/17 | Equipment problem reorder equipment | 5 days |
3/24/17 | 3/25/17 | Pre-production coverage/b-roll | 2 days |
3/26/17 | 3/27/17 | Pre-production interview no show reschedule | 2 days |
4/1/17 | 4/2/17 | Pre-production | 2 days |
4/4/17 | 4/6/17 | Pre-production | 2 days |
4/8/17 | 4/13/17 | Pre-production | 5 days |
4/14/17 | 4/21/17 | Pre-production | 7 days |
4/22/17 | 4/25/17 | review footage | 3 days |
4/26/17 | 4/31/17 | reshoot footage/ script research | 6 days |
5/1/17 | 5/14/17 | editing/poster making | 14 days |
Old Schedule
Start Date | End Date | Description | Duration |
1/21/17 | 2/20/17 | Prep/Planning | 31 days |
2/1/17 | 2/20/17 | Ordering Equipment/Accessories | 20 days |
3/21/17 | 3/23/17 | Interview/practice | 2 days |
3/18/17 | 3/18/17 | Outdoor shooting of line up/coverage shots | 1 day |
3/26/17 | 3/27/17 | Interview/practice | 2 days |
3/24/17 | 3/25/17 | Shooting Line up/ interview/practice/coverage shots | 2 days |
4/1/17 | 4/2/17 | Interview/ practice | 2 days |
4/4/17 | 3/6/17 | interview/practice | 2 days |
4/8/17 | 4/13/17 | review shoots/Re-shoots if needed | 5 days |
4/14/17 | 4/28/17 | Editing phase 1,2,3,4 | 15 days |
5/1/17 | 5/10/17 | poster making/editing/finial video editing. | 10 days |