9/7: Preliminary planning
9/14: Start of project. Introductory page
9/21: Finish introductory page, start page scroll button
9/28: Finish buttons, integrate restaurant site into project
10/5: Finish restaurant site integration, start gym site integration
10/12: Finish gym site integration, start LinkTree clone integration
10/19: Finish LinkTree clone integration, start contact form and external links
10/26: Finish contact form and external links
11/2: Testing phase, trying on different browsers, and devices
11/9: Create repository and upload to Github
Budget:
No cost.